Methacton High School Renovation Project
Project Highlights
- New classroom wing and Fab-Lab
- New auditorium and performing arts spaces
- New 8-lane pool and wellness center
- New life skills apartment
- New front entrance and student commons
- Traffic flow and parking improvements
- $113 million estimated project cost
Project Timeline
- August 2026 - January 2027: Construction Documentation
- February 2027 - April 2027: Bidding
- May/June 2027 - July 2030: Construction
Important Upcoming Dates
September 22, 2026 - Board Work Session
MHS LGI - 7:00 pm
Project Update
October 28, 2026 - Act 34 Hearing
MHS LGI - 7:00 pm
Current Phase: Construction Documents
Latest Updates
-
The Board of School Directors approved advancing the High School renovation project into the Construction Documents phase at the August 25, 2026 Regular Meeting.
-
The project architects and engineers are preparing the drawings and specifications to go out to bid.