Current Phase: Schematic Design

Latest Updates

  • The Board of School Directors, at their October 28, 2025 meeting, unanimously provided approval for the High School Renovation Design Team to proceed forward into the schematic design phase.
  • The Schematic Design Phase takes the proposed renovation concept from initial rough sketches and drawings into architectural and spatial layouts with greater detail, more refined cost estimates, and clearer project phasing and timelines.
  • The Board of School Directors will be presented with the outcome of the schematic design in January or February 2026, at which time they could determine to proceed to the next phase called Design Development. During the design development phase, the district will meet with staff and students and host several public input sessions to keep the community informed and gather feedback to help guide the project’s future development.


Renovation Plans 

The Methacton High School Renovation Project is rooted in addressing core building systems including roofing, windows, masonry, ventilation, heating, air conditioning and dehumidification systems, electrical systems, safety and security systems, and accessibility. The plan further addresses traffic flow, parking, and a pool and wellness center, along with developing life skills space, common space, performing arts and STEM spaces.

The concept plan is organized to provide a project-based approach to addressing the campus and high school building over time starting with the areas most in need, then progressing over time from the oldest areas of building to newer areas of the building. This approach allows the district to better align the costs of the project, currently estimated at $114 million, into the annual budget.

Resources from Renovation Feasibility & Planning Phase


 

The Path to Renovation

In October of 2023, following the acceptance of a facilities assessment of Methacton High School, the Board of School Directors embarked on a process to address identified facility needs and respond to student, staff and community feedback about the condition of the facility and campus at that time. That process began with considering new construction concepts based on the feedback from within the school community.

In February of 2025, after thorough financial analysis and due diligence, the Methacton Board of School Directors paused on moving forwards to the next phase of the new Methacton High School campus project to reassess our approach to addressing facility needs. The projected cost had escalated from an estimated $170 million to $213 million, posing unsustainable fiscal risk, including potential annual deficits of $3–8 million within five years. Therefore, the Board determined that a full rebuild of the high school and campus was not financially viable at that time.

While our facility needs remained urgent, our commitment to educational excellence demanded a more fiscally responsible path. As such, the Board of School Directors dediced to move forward with exploring alternative renovation solutions that prioritize student and staff needs without compromising Methacton’s long-term financial health.

The work to date has provided valuable insights—especially regarding educational space needs—that will inform a more strategic, cost-effective plan moving forward. The district continues to collaborate with our design partners, CHA and Schrader Group, to develop solutions that support safety, accessibility, and modern learning environments.

This decision reflects our obligation to both students and taxpayers: to deliver high-impact outcomes while safeguarding the district’s financial future.

Sequence of Events

  • 2018 - Moore Engineering conducts Heating/Ventilation & Air Conditioning (HVAC) and humidity evaluation of all school buildings 
  • 2020 - High School Heating/Ventilation & Air Conditioning (HVAC) project scope developed with bid at $9.3M (placed on hold to address Eagleville Elementary School)
  • 2022 - High School HVAC project re-developed with additional scope (chiller/boiler) projected at $25M
  • 2023 - Accepted Updated Facilities Assessment with Conditions Report
  • 2023 - Issued call for participation on the Methacton High School Campus Planning Committee (MHSCPC) to gather input
  • 2024 - February - Planning Committee issued report and presented pre-conceptual new construction scenarios
  • 2024 - Developed new construction concepts and associated costs
  • 2025 - January - Updated new construction costs approaching $220M
  • 2025 - March - Board votes to pivot towards seeking renovation options
  • 2025 - April - Board establishes priorities to address under renovation
  • 2025 - August - Board is presented with four renovation options
  • 2025 - October - Board votes to move to schematic design phase 

Subsections

Key Dates & Events

Check back soon for upcoming dates